(1) Do a good job before the start of the inspection.
1) Confirm that the compressor is installed and piping meets all requirements.
2) Confirm that the power supply line is correct and connect the grounding wire.
3) Loosen the anti-vibration table, support frame or transport fixing bolts on the motor.
4) Check if the oil level in the oil and gas tank is at the specified oil level.
5) Add about 0.5 liters of lubricating oil from the intake valve and turn the air compressor several times to prevent the oil from burning in the air compressor during start-up. Pay special attention to prevent foreign matter from falling into the compressor body to avoid damage to the compressor.
6) Send power to the compressor control panel. If the power phase does not match, the LCD displays the “Power Phase Error” message. In this case, just turn off the power supply and adjust any two of the power cables. Test if the main voltage is correct and whether the three-phase voltage is balanced.
7) Open the compressor air outlet and confirm that the drain valves in the unit are closed. The water-cooled model opens the cooling water inlet and outlet valve port.
8) Turn on the supporting equipment first, such as dryer, cooling tower, etc., and confirm that it is working properly.
(2) Operation test. Press the “NO” button to turn the compressor and immediately press the “Emergency Stop button” to confirm the compressor steering. For correct steering, please refer to the arrow on the compressor body. The cooling fan also needs to pay attention to the steering. Although the compressor has been tested in the production process, the steering test is still an important step in the new machine test.
(3) Start. Press the "NO" button again to start the compressor operation. For the first time, the air load test of the air compressor was carried out for load test.
(4) Observe whether the instrument and indicator light are normal. If there is abnormal sound, vibration or leakage, immediately press the “emergency stop button” to stop the maintenance.
(5) Operating temperature adjustment. After the compressor is running for 40 minutes, adjust the opening degree of the return valve to control the exhaust temperature of the heavy truck at 80 °C (the air-cooled type does not need to be adjusted). When adjusting, gradually reduce the opening degree of the return valve, and adjust the opening degree after reacting the exhaust temperature of the compressor.
(6) Stop. Press the “OFF” button, and the compressor will stop running after 15s delay.
(7) Check the pressure switch unloading and load pressure setting values. According to the trial operation plan, determine whether to perform the performance and efficiency experiments of the air compressor.
(8) The air compressor is put into continuous operation for not less than 4 hours, and there is no abnormality in the work.